- PAIMANA Portal Tracks 1,941 Infrastructure Projects worth ₹41.50 lakh crore as of March 2026
New Delhi.: The Ministry of Statistics and Programme Implementation (MoSPI) continues to strengthen monitoring of Central Sector infrastructure projects through its PAIMANA platform, enabling improved tracking, timely reviews, and data-driven decision-making across Ministries. The portal tracks 1,941 Infrastructure Projects worth of ₹41.50 lakh crore as of March 2026.
Key Highlights
|
- 1,941 ongoing infrastructure projects include 786 Mega projects (project cost of ₹1,000 crore & above) with an original cost of ₹30.48 lakh crore, and 1,155 Major projects (project cost below ₹1,000 crore and up to ₹150 crore) amounting to ₹5.41 lakh crore.
- Physical and financial progress broadly move in tandem, with a large number of projects clustered at the initial (0–20%) and advanced (81–100%) stages, indicating a pipeline of newly-started projects alongside many nearing completions. While physical progress exceeds financial progress in the 81–100% range, financial progress is relatively higher in the early stages, reflecting upfront expenditure patterns in project implementation.

2. Ministry/ Departments-wise progress of Infrastructure Projects
- Ministry of Road Transport & Highways accounts for the highest number of projects, with 1120 projects (58%), and a share of total revised project cost of ₹10.61 lakh crore (26%), highlighting its central role in national infrastructure development.
- Ministry of Railways is implementing 244 projects (13%), and also commands the largest share of total revised project cost at ₹8.37 lakh crore (20%).
- Ministry of Coal accounts for implementing 127 projects (6%), with a total revised project cost of ₹2.46 lakh crore (6%).
- The Ministry of Petroleum & Natural Gas, Ministry of Power, Ministry of Housing & Urban Affairs, and the Department of Water Resources, River Development & GR are implementing 108, 98, 53, and 49 projects, with associated revised costs of ₹5.11 lakh crore, ₹5.14 lakh crore, ₹3.6 lakh crore, and ₹2.26 lakh crore, respectively.
- The remaining 142 projects (7%), with a total revised cost of ₹3.96 lakh crore (10%), are distributed across various Ministries/Departments including Higher Education, Civil Aviation, Steel, Telecommunications, Labour & Employment, Ports, Shipping & Waterways, Health & Family Welfare, Mines, DPIIT, and Sports. (Refer Annexure I)

3. Sector-wise (as per DEA’s Harmonized Master List of Infrastructure) Progress of Infrastructure Projects
- Transport & Logistics remains the dominant sector, accounting for 55% of total revised cost (₹22.66 lakh crore) across 1,428 projects (73 % of the total Projects), underscoring the central role of Roads & Highways, Railways, Aviation, Urban Public Transport, Shipping, and Inland Waterways in economic integration and logistics efficiency.
- The Energy sector follows with 26% of aggregated revised cost (₹10.79 lakh crore) across 212 projects, reflecting sustained emphasis on Oil & Gas infrastructure, electricity generation, transmission and distribution networks, and energy storage systems.
- Communication infrastructure, with a revised cost of ₹2.73 lakh crore (7%) across 12 projects, represents targeted interventions aimed at strengthening digital connectivity.
- Water & Sanitation projects account for ₹2.31 lakh crore (5%) across 71 projects, highlighting continued focus on essential urban services.
- Social & Commercial infrastructure, comprising 73 projects with a revised cost of ₹0.79 lakh crore (2%), reflects selective investments in education, healthcare, real estate, and tourism, hospitality and wellness.
- Projects classified under ‘Others’, amounting to ₹2.20 lakh crore (5%) across 145 projects, indicate diversification across sectors such as coal, steel, metals, and mining.
(Refer Annexure II)

4. Completed Projects and New Additions
- During March 2026, 25 projects were commissioned, including major assets in Road Transport & Highways, Petroleum & Natural Gas, Housing & Urban Affairs, Railways, Power, Ports, Shipping and Waterways, Telecommunications, Steel and Labour and Employment. Notable commissioned projects include the “Delhi-Ghaziabad-Meerut Regional Rapid Transit System [RRTS] corridor” (₹ 30,274 crore) from Ministry of Housing & Urban Affairs, and the “Tehri Pumped Storage Plant Project [4×250 MW] (₹ 8,339 crore) from Ministry of Power.
- During March 2026, 12 additional projects from MoRTH were brought under the monitoring of PAIMANA.
5. Next date of Press Release: Flash Report for the month of April 2026 would be released on 25th May 2026.
Note
- The press release summarizes highlights from the MoSPI’s Flash Report (March 2026) on Central Sector Infrastructure Projects (₹150 crore and above), available at https://www.ipm.mospi.gov.in/ or via the QR code.
- PAIMANA is a centralized web-based portal for monitoring of Central Sector Infrastructure Projects worth ₹150 crore and above. Operating on the “one data, one entry” principle, it integrates with DPIIT’s IPMP portal via APIs to automatically update more than 70% of project data from various Ministries/Departments. PAIMANA also serves as a national repository designed to standardize infrastructure monitoring and support informed decision-making for nation-building.
Annexure I
Ministry/ Departments-wise progress of Central Sector Infrastructure Projects
| S. No | Ministry/ Department | Project Count | Revised Cost
(₹ Lakh cr.) |
Cumulative Expenditure (₹ Lakh cr.) |
| 1 | Ministry of Road Transport & Highways | 1120 | 10.61 | 3.52 |
| 2 | Ministry of Railways | 244 | 8.37 | 5.69 |
| 3 | Ministry of Coal | 127 | 2.46 | 0.80 |
| 4 | Ministry of Petroleum & Natural Gas | 108 | 5.11 | 2.99 |
| 5 | Ministry of Power | 98 | 5.14 | 1.94 |
| 6 | Ministry of Housing & Urban Affairs | 53 | 3.60 | 1.98 |
| 7 | Department of Water Resources, River Development & GR | 49 | 2.26 | 1.61 |
| 8 | Department of Higher Education | 29 | 0.14 | 0.08 |
| 9 | Ministry of Civil Aviation | 26 | 0.23 | 0.11 |
| 10 | Ministry of Health & Family Welfare | 23 | 0.21 | 0.08 |
| 11 | Ministry of Steel | 19 | 0.23 | 0.10 |
| 12 | Ministry of Labour and Employment | 12 | 0.03 | 0.02 |
| 13 | Department of Telecommunications | 12 | 2.73 | 0.77 |
| 14 | Ministry of Ports, Shipping and Waterways | 11 | 0.22 | 0.15 |
| 15 | Ministry of Mines | 6 | 0.10 | 0.07 |
| 16 | Department for Promotion of Industry & Internal Trade | 3 | 0.05 | 0.01 |
| 17 | Department of Sports | 1 | 0.01 | 0.01 |
| Total | 1941 | 41.50 | 19.93 |
Annexure II
Sector-wise (as per DEA’s Harmonized Master List of Infrastructure) progress of Central Sector Infrastructure Projects
| S. No | HML Category | Project Count | Revised Cost (₹ Lakh cr.) | Cumulative Expenditure (₹ Lakh cr.) |
| 1 | Transport & Logistics | 1428 | 22.66 | 11.28 |
| 2 | Energy | 212 | 10.79 | 5.21 |
| 3 | Water & Sanitation | 71 | 2.31 | 1.65 |
| 4 | Communication | 12 | 2.73 | 0.77 |
| 5 | Social & Commercial | 73 | 0.79 | 0.34 |
| 6 | Others | 145 | 2.21 | 0.67 |
| Total | 1941 | 41.50 | 19.93 |